Running Segment Changes Report

  1. Go to the Projects list tab (refer to Opening Projects).
  2. Select and open the project.
  3. Click Segment Changes Report.    

    The Segment Changes Report dialog box appears.

  4. Make the required selections.
  5. Click Export.

    The following example shows an exported Segment Changes report.

    Running a Segment Changes Report also presents a Segment Changes Summary pop-up as shown.

  6. Click OK.