Running Segment Changes Report

To run and export a Segment Changes report from the Project Files tab:

  1. Go to the Projects list tab (refer to Opening Projects).
  2. Select and open the project.
  3. Click Segment Changes Report (as shown).

    The Segment Changes report dialog opens.

  4. Make the required selections.

    The following is an example of running a Segment Change report.

    Figure 1. Segment Change Report Example

  5. Click Export.

    The following example shows the exported Segment Changes report.

    Figure 2. Segment Change Report Export Example

    Executing a Segment Changes Report also presents a Segment Changes Summary pop-up as shown.

    Figure 3. Segment Change Report Summary Example

  6. Click OK.